Design & Planning As Built Client Portal Part L Photo Evidence 01386 365145 Book a Test
BTS 3/2018 · HTM 03-01 · Healthcare Compliance

Isolation Facility
Air Tightness Testing.

ATTMA-accredited air permeability testing to BTS 3/2018 for isolation suites, operating theatres, aseptic pharmacy preparation, and containment facilities. Certificates suitable for commissioning, handover, and periodic verification against HTM 03-01.

2.5
m³/hr/m² @ 50 Pa
BTS 3/2018 target
HTM 03-01
Referenced testing
methodology
ATTMA
Accredited test
engineers

Book a Test

BTS 3/2018 testing is required for HTM 03-01 compliance. Early engagement lets us align testing with your commissioning programme.

Thanks — we'll come back to you within one working day with availability and pricing.

Accredited & Registered ATTMA Accredited Elmhurst Approved Assessor SITMA Accredited BPEC Registered DesignBuilder

What is BTS 3/2018 testing and why does an isolation facility need it?

Isolation facilities rely on a controlled pressure differential to contain airborne pathogens or protect vulnerable patients. That differential can only be maintained if the room envelope is measurably airtight — BTS 3/2018 sets the target and defines how to prove it.

Infection control integrity
A negative-pressure isolation room contains airborne pathogens; a positive-pressure protective room keeps them out. Excessive envelope leakage breaks both control strategies — infectious agents migrate to adjacent clinical areas or protection is lost for immunocompromised patients.
HTM 03-01 compliance
The Health Technical Memorandum HTM 03-01 references BTS 3/2018 as the accepted air permeability testing methodology. A test certificate is a routine requirement for commissioning, handover, and post-refurbishment sign-off in NHS estates.
Predictable ventilation performance
The room’s ventilation system is designed around a defined leakage assumption. Higher-than-expected leakage means the design air change rates and pressure differentials cannot be achieved — the mechanical system will not perform as commissioned.
BTS 3/2018 target
2.5
m³/hr/m² at 50 Pa — recommended overall envelope leakage

The BTS 3/2018 recommended limit for overall air leakage of an isolation suite is 2.5 m³/hr/m² at 50 Pa. This is the whole-envelope permeability figure the built room needs to achieve to be considered compliant with the BSRIA methodology referenced by HTM 03-01.

Individual project specifications, infection-control policies, or the client’s estates team may set a tighter limit for particular room types — for example, some high-containment or protective isolation rooms are designed to a stricter figure. Always confirm the target with the design team and infection-control lead before testing.

Alongside the overall envelope test, BTS 3/2018 gives methods for measuring leakage through specific paths — door edges, door grilles, transfer grilles — so that each path can be compared against the design assumptions used by the ventilation designer. Full standard available free from BSRIA.

What are the two stages of a BTS 3/2018 test?

BTS 3/2018 defines an overall envelope test and, where required, targeted measurements along individual leakage paths. Together they give a complete picture of the room’s air permeability and where any excess leakage is coming from.

01
Overall envelope
Whole-suite permeability test

The overall envelope test measures total leakage from the isolation suite at a defined reference pressure of 50 Pa (or the pressure specified in the design brief). It gives the headline number to compare against the BTS 3/2018 target of 2.5 m³/hr/m².

  • Review room drawings, ventilation strategy, and BTS 3/2018 or client-specific target
  • Isolate the room’s ventilation system and seal supply/extract terminals
  • Set up calibrated fan unit and pressure taps at defined reference points
  • Pressurise (or depressurise) the room to the reference pressure differential
  • Measure airflow and differential; calculate whole-envelope air permeability in m³/hr/m²
  • Compare against BTS 3/2018 limit and any project-specific tighter target
02
Path-specific
Door & grille leakage measurement

Where the design assumes a defined leakage across specific paths — typically the doors, door grilles, or transfer grilles that the ventilation strategy relies on — those paths can be measured individually to compare against the design specification.

  • Identify design leakage assumptions for each measured path from ventilation drawings
  • Isolate the path to be measured (temporarily seal or mask other openings)
  • Measure airflow through the path at the specified pressure differential
  • Compare measured leakage against the design value for each path
  • Where a path leaks more than designed, identify sealing or component adjustment required
  • Issue full test report with envelope result, individual path results, and compliance certificate

When is a BTS 3/2018 test required?

Testing is required at commissioning of any new or refurbished isolation facility, and periodically thereafter to verify continued compliance. Both are expected under HTM 03-01 as part of the estates ventilation validation regime.

New build & refurbishment
Commissioning testing — required at completion

A BTS 3/2018 test at commissioning demonstrates that the as-built isolation suite envelope achieves the recommended air permeability limit before the room is put into clinical use. Certification is normally required as part of the HTM 03-01 validation package alongside ventilation flow rate testing and other commissioning documents.

Isolation rooms are typically completed by several different trades — carpentry, glazing, ductwork, medical gases, electrical — and each introduces potential leakage paths. The envelope has to be tested as a whole, once complete, because individual component certification does not guarantee an airtight installed system.

We recommend engaging us during design and again before final finishes are applied. Early involvement means design assumptions can be validated, and any remediation is straightforward while penetrations remain accessible.

Existing facilities
Periodic verification & post-works retesting

Over time, minor maintenance, medical gas or IT rewiring, ceiling access, door adjustments, and general wear can all affect envelope integrity. HTM 03-01 and estates governance regimes therefore expect isolation facilities to be periodically re-tested to verify continued compliance.

Retesting is also typically required after any refurbishment, plant replacement, or minor works that penetrate the envelope — even if the works appear cosmetic. A rehung door, replaced ceiling tile, or new data cable can meaningfully change the leakage rate.

Test certificates are retained as part of the facility’s ventilation validation records for audit, inspection, and infection-control governance purposes.

Why do isolation facilities fail BTS 3/2018 testing?

Most BTS 3/2018 failures come down to a handful of recurring paths — nearly all of them straightforward to address before finishes are applied, and disruptive to fix once the room is in clinical use. We provide pre-test guidance at booking and can carry out a walkover inspection to identify likely issues before formal pressurisation.

The core principle: the internal face of the envelope is the primary air seal. Every service penetration, joint, and door/frame junction on the room side must be continuously sealed. Sealing only from the ceiling void or corridor side leaves paths that show up on the test but are hidden until testing exposes them.

Where the design team has specified an infection-control ceiling with sealed access panels, sealed light fittings, and impervious wall linings, this is normally a good indicator that acoustic and hygiene detailing has already been thought through. Where those details are missing, expect a first-pass failure.

Door edge & threshold seals Doors are the largest single leakage path in most isolation rooms. Compression seals along all four edges (including drop-down or fixed thresholds) are essential. Common failures include worn or damaged seals, missing threshold seals, and doors that have been re-hung without adjusting the closer.
Unsealed service penetrations Medical gas pipework, sprinkler drops, data and electrical cables, and nurse-call wiring all cross the envelope. Each penetration needs to be individually sealed on the room side — cable bundles that are not separated and mastic-sealed are among the most persistent leakage paths.
Glazing perimeter & observation windows Observation panels and viewing windows must be sealed continuously around the frame on the internal face. Frames that have been silicone-sealed on the corridor side only, or where the glazing bead has been fitted without a wet seal, will leak. Vision panels in doors are equally common failure points.
Ceiling grid & access panel gaps Where an infection-control ceiling is used, the perimeter of the grid must be sealed and all access panels gasketed. Standard suspended ceilings without gasketed panels are almost never airtight enough for BTS 3/2018 targets and are a leading cause of failures on refurbishment projects.
Transfer & door grilles unspecified for pressure Where the ventilation strategy relies on a transfer grille or door grille to permit designed leakage, the grille’s free area must match the design assumption. Grilles that are oversized, missing, or blocked will make the pressure differential unachievable even if the rest of the envelope passes.

The framework for isolation facility air permeability testing.

BTS 3/2018 sits alongside HTM 03-01 and broader healthcare ventilation guidance. Together they define both the target performance and the estates governance regime around ongoing verification.

BSRIA Technical Standard
BTS 3/2018
Air permeability testing of isolation facilities. Published December 2018. Sets the 2.5 m³/hr/m² @ 50 Pa recommended limit and defines methods for measuring both overall envelope leakage and path-specific leakage across doors and grilles.
Health Technical Memorandum
HTM 03-01
Specialised ventilation for healthcare premises. The primary NHS estates guidance document for hospital ventilation design, commissioning, and validation — references BTS 3/2018 as the accepted air permeability test methodology.
Related HTM guidance
HTM 00 & HTM 05-03
Broader estates and facilities management framework covering healthcare premises. HTM 05-03 addresses fire safety and life safety, complementing HTM 03-01 on ventilation and infection control.
British Standard
BS EN 12237 & related
Ductwork leakage testing standards used alongside BTS 3/2018 where ventilation ductwork forms part of the isolation strategy. Applied for the extract, supply, and pressure-relief ducting connecting the room to plant.
Care Quality Commission
CQC estates expectations
CQC inspections of NHS trusts and independent healthcare providers expect documented ventilation validation records for isolation and treatment areas — including current BTS 3/2018 test certificates and periodic recertification.
Best-practice guidance
SHTM 2025 (Scotland)
Scottish Health Technical Memorandum for ventilation in healthcare premises. The Scottish equivalent to HTM 03-01, referenced for isolation facility validation across NHS Scotland.

BTS 3/2018 air permeability testing across the Midlands and South West.

Isolation facility testing needs to be booked around clinical availability — we work with estates and infection-control teams to schedule around ward decant, out-of-hours access, and post-refurbishment handover windows.

Birmingham & West Midlands

BTS 3/2018 testing for NHS trusts and independent hospitals across Birmingham, Solihull, Coventry, Wolverhampton, and the wider West Midlands — including UHB, SWBH, and Sandwell & West Birmingham estates. Isolation suites, operating theatres, and containment facilities.

Bristol & South West

Isolation facility testing for hospitals and specialist units across Bristol, Bath, South Gloucestershire, and the surrounding South West. HTM 03-01 validation for new build and refurbishment projects.

Worcestershire

Based in Worcester — BTS 3/2018 testing across Malvern, Droitwich, Evesham, Bromsgrove, and Redditch. Rapid mobilisation for local hospitals and pharmacy aseptic units.

Gloucestershire

Isolation facility air permeability testing across Cheltenham, Gloucester, Stroud, Tewkesbury, and the Cotswolds. Certificates accepted for HTM 03-01 estates validation records.

Oxfordshire

BTS 3/2018 testing across Oxford, Banbury, Bicester, Witney, and the wider Oxfordshire area — NHS trusts, university teaching hospitals, and specialist research facilities.

Wider England & Wales

BTS 3/2018 testing delivered nationally where project scale or programme justifies the travel. Regularly working with NHS trusts and independent hospital groups outside our core regions.

Looking for BTS 3/2018 testing near you? Whether it’s a new isolation suite at commissioning, an operating theatre refurbishment, a pharmacy aseptic room, or periodic HTM 03-01 revalidation. We deliver clear reports with the certificate you need for the estates record. Call 01386 365145 or email us to book.

Common questions about BTS 3/2018 testing.

BTS 3/2018 is a technical standard published by BSRIA in December 2018, titled “Air permeability testing of isolation facilities”. It sets recommended air leakage limits for isolation suites and other healthcare facilities where infection control depends on maintaining pressure integrity.

It also describes how to measure whole-envelope leakage as well as leakage through specific paths such as doors and door grilles. Referenced by HTM 03-01 as the accepted methodology for validating air tightness of isolation suites, operating theatres, aseptic pharmacy preparation rooms, and containment facilities.

BTS 3/2018 recommends an overall envelope air leakage limit of 2.5 m³/hr/m² at 50 Pa for isolation suites in healthcare facilities. The standard also gives guidance on measuring leakage through specific paths so those individual routes can be compared against design specifications.

Individual project specifications, HTM addenda, or the client’s estates and infection-control team may set a tighter target — the applicable value should always be confirmed in the design brief before testing.

An isolation suite works by controlling the direction and rate of air movement between the suite and adjacent spaces — a negative-pressure infection isolation room contains airborne pathogens, while a positive-pressure protective isolation room keeps them out. Both depend on a well-defined envelope with predictable leakage.

Excessive or unaccounted-for leakage means the room’s ventilation system cannot achieve the design pressure differential, air can bypass HEPA filtration, and airborne pathogens can migrate to or from other clinical areas. BTS 3/2018 testing verifies that the built envelope will support the intended airflow strategy.

BTS 3/2018 testing is typically carried out at commissioning, once the envelope is sealed and services are terminated but before final finishes are applied. Testing at this stage means any leakage found can be traced and sealed while penetrations, ceiling grids, and joints are still accessible.

Repeat testing may then be required after finishes, after handover, and periodically through the building’s operational life to verify continued compliance following maintenance or minor works.

A failure result identifies the total leakage rate exceeding the BTS 3/2018 target. Remediation involves locating the leakage paths — typically door seals, glazing perimeter seals, ceiling grid junctions, service penetrations (medical gases, data cables, sprinkler pipework), and any transfer grilles or observation windows — and sealing them individually. We then re-test the envelope to confirm compliance.

Where practical, we recommend a preliminary walkover and thermal or smoke-pencil survey before formal pressurisation so that obvious paths can be sealed in advance.

They use similar equipment — a calibrated fan and pressure gauges — but measure different things. Part L air tightness testing (to ATTMA TSL Issue 1) measures whole-envelope leakage of a dwelling or non-domestic building for energy compliance.

BTS 3/2018 testing measures the air permeability of a single isolation suite or room within a larger building, to verify infection-control performance rather than energy compliance. The same accredited team can perform both, but the test procedures, reporting, and pass criteria differ.

Book early to align with commissioning

Isolation facility to test?
Book it into your programme.

Engaging us before final finishes go in gives the best chance of a first-time pass. We work around clinical availability and estates handover windows.

Book a Test →

Get in touch

Tell us about your project and we'll confirm our availability, provide a quote, and advise on the optimal testing programme for your schedule.

Enquiry received

We'll review your details and come back within one working day.